Page 21 - ATEN Data Centers Server-Rooms Field Guide
P. 21

Unmanned Server Management








        6         Flexible Process Control Server Management for




                  Unmanned Facilities






         Due to the high cost of personnel, and strict limits to
         headcount due to safety regulations, an oil drilling

         platform needed multiple industrial process computers

         to be safely located in an unmanned server room
         onshore, while still being accessible from 5 separate

         control rooms in various locations throughout the

         production facilities. Furthermore, in case of future
         operational expansion, the system needed to incorporate

         both point-to-point and multipoint-to-multipoint KVM

         extender connections. The setup required a specialist in

         process automation of industrial plants, with a focus on
         integrating DCS, SCADA/HMI and PLC solutions with

         remote IT management.